Status of Roadway Capacity Projects in
Northwest Florida and Southwest Alabama
Many roadway capacity projects in northwest Florida have recently been completed, are underway, or are scheduled to commence construction in the next five years. In addition, four projects in southwestern Alabama are scheduled to begin construction in the next five years. The following is an overview of the Long Range Transportation Plans (LRTPs) for the Florida-Alabama, Okaloosa-Walton, and Bay County Transportation Planning Organizations (TPOs), the Florida Department of Transportation’s historical, existing, and tentative Work Programs, the Alabama Department of Transportation’s Work Program, and locally funded capacity projects.
FLORIDA-ALABAMA TRANSPORTATION PLANNING ORGANIZATION
Florida-Alabama Transportation Planning Organization’s study area consists of the southern portions of Escambia and Santa Rosa County as well as portions of the Lillian and Orange Beach areas in Baldwin County, Alabama.
Recently Completed Projects
|
|||
Project | From | To | Improvement |
SR 180 (Canal Road) |
Foley Beach Express |
SR 161 (Orange Beach Boulevard) |
5 lanes |
Olive Road |
Gregg Road |
Yancey Avenue |
2 lanes with bidirectional turn lanes in the center |
Olive Road |
Yancey Avenue |
Johnson Avenue |
2 lanes with bidirectional turn lanes in the center |
Gregory Street/Bayfront Parkway/17th Avenue |
Gregory Street/Bayfront Parkway |
17th Avenue |
Flyover/Roundabout |
Nine Mile Road |
Pine Forest Road |
US 29 |
4 lanes |
Nine Mile Road |
Beulah Road |
I-10 |
4 lanes |
Nine Mile Road |
I-10 |
Pine Forest Road |
4 lanes |
US 29 |
I-10 |
North of Nine Mile Road |
6 lanes |
Pea Ridge Connector |
US 90 |
Hamilton Bridge Road |
4 lanes |
Pensacola Bay Bridge |
Bay Bridge Drive |
17th Avenue |
6 lanes |
Projects Currently Under Construction | |||||
Project | From | To | Start Date | End Date | Improvement |
US 29 |
West Scott Street |
US 90 (Cervantes Street) |
July 2023 |
Spring 2025 |
Road Diet from 4 to 2 Lanes |
Longleaf Drive |
Pine Forest Road |
East of Wymart Road |
November 2022 |
February 2025 |
2 Lanes with bidirectional turn lanes in the center |
US 98 |
Bayshore Road |
Portside Drive |
Fall 2021 |
Summer 2025 |
6 lanes |
Waterway Bridge |
SR 180 (Canal Road) |
CR 4 |
Winter 2022 |
Fall 2026 |
2 lanes |
US 29/I-10 Phase II |
US 29 |
I-10 |
Spring 2024 |
Summer 2030 |
Overpass |
Projects Scheduled to be Under Construction within Five Years | |||
Project | From | To | Improvement |
Frank Reeder Road |
Beulah Road |
End of the road near I-10 |
3 lanes |
SR 180 (Canal Road) |
Beaver Creek Lane |
Foley Beach Express |
5 lanes |
Waterway Extension |
CR 4 |
Foley Beach Express |
2 lanes |
Canal Road Intersection at SR 161 |
SR 180 (Canal Road) |
SR 161 (Orange Beach Boulevard) |
Intersection |
I-10 |
Alabama State Line |
East of East Bound Weigh Station |
6 Lanes and new interchange at Beulah Road |
I-10 |
East of East Bound Weigh Station |
Nine Mile Road |
6 Lanes and new interchange at Nine Mile Road |
OKALOOSA-WALTON TRANSPORTATION PLANNING ORGANIZATION
Okaloosa-Walton Transportation Planning Organization’s study area is a little north of Crestview and DeFuniak Springs and covers most of the southern portions of both Okaloosa and Walton Counties.
Recently Completed Projects | |||
Project | From | To | Improvement |
US 331 |
North End of Choctawhatchee Bay |
South End of Choctawhatchee Bay |
4 lanes |
US 331 |
North End of Choctawhatchee Bay |
SR 20 |
4 lanes |
US 331 |
SR 20 |
I-10 |
4 lanes |
Foy Shaw Parkway |
US 90/ E. James Lee Boulevard |
John Givens Road/Skyline Drive |
2 lanes |
CR 280B Connector Road |
CR 280A |
US 331 |
2 lanes |
US 98 |
Emerald Bay Drive |
Tang-O-Mar Drive |
6 lanes |
US 98 |
Mack Bayou Boulevard |
CR 30A West |
6 lanes |
PJ Adams Parkway |
SR 85S |
Wild Horse Drive |
4 lanes |
Projects Currently Under Construction | |||||
Project | From | To | Start Date | End Date | Improvement |
PJ Adams Parkway |
Wild Horse Drive |
I-10 |
August 2021 |
Winter 2025 |
4 lanes |
Southwest Bypass |
Fallen Heroes Way |
US 90 |
September 2021 |
April 1, 2025 |
4 lanes |
Fallen Heroes Way |
Antioch Road |
Physicians Drive |
September 2021 |
April 1, 2025 |
2 lanes |
I-10 West/PJ Adams Parkway |
I-10 |
PJ Adams Parkway |
Fall 2022 |
Winter 2025 |
Interchange |
Brooks Bridge |
Perry Avenue |
Pier Road |
July 2022 |
Summer 2027 |
6 lanes |
Projects Scheduled to be Under Construction within Five Years | |||
Project | From | To | Improvement |
Destin Crosstown Connector |
Benning Drive | Beach Drive | 2 lanes |
BAY COUNTY TRANSPORTATION PLANNING ORGANIZATION
Bay County Transportation Planning Organization’s study area is the entirety of Bay County.
Recently Completed Projects | |||
Project | From | To | Improvement |
SR 30/US 98A (Front Beach Road |
South Thomas Drive/Beach Boulevard |
North Thomas Drive |
Multi-Modal |
South Thomas Drive/Beach Boulevard |
SR 30/ US 98A (Front Beach Road) |
North Thomas Drive |
Multi-Modal |
Front Beach Road |
South Thomas Drive |
Richard Jackson Boulevard |
Multi-Modal |
Powell Adams Road |
SR 30A/US 98 (Back Beach Road) |
L.C. Hilton Drive |
4 lanes |
Bay Parkway Phase I |
SR 79 |
US 98 (Panama City Beach Parkway) |
2 lanes ROW for 4 lanes |
Bay Parkway Phase II |
Pier Park Drive |
Nautilus Road |
2 lanes ROW for 4 lanes |
Colony Club Connector |
Nautilus Street |
Fairway Boulevard |
2 lanes |
Jenks Avenue |
23rd Street |
Baldwin Road |
5 lanes |
US 98/23rd Street Overpass |
US 98 |
23rd Street |
Overpass |
Jenks Avenue |
Baldwin Road |
SR 390 |
5 lanes |
SR 390 |
Baldwin Road |
Jenks Avenue |
6 lanes |
SR 390 |
Jenks Avenue |
SR 77 |
6 lanes |
Titus Road |
SR 390 |
CR 2321 |
2 lanes |
SR 388 |
SR 79 |
East of Northwest Florida Beaches Airport |
4 lanes |
Projects Currently Under Construction | |||||
Project | From | To | Start Date | End Date | Improvement |
Tyndall Air Force Base/US 98 Overpass |
Tyndall Air Force Base |
US 98 |
November 2019 |
Early 2025 |
Overpass |
South Arnold Street |
Back Beach Road |
Front Beach Road |
May 2021 |
Early 2025 |
4 lanes with roundabout at Front Beach at S. Arnold St. |
Front Beach Road |
South Arnold Street |
Lullwater Drive |
May 2021 |
Mid 2024 |
Multi-Modal |
Gulf Coast Parkway |
US 98 |
Star Avenue |
November 2022 |
Spring 2025 |
4 lanes |
SR 390 |
23rd Street |
Baldwin Road |
December 2019 |
Spring 2026 |
6 lanes |
US 98 (Panama City Beach Parkway) |
Mandy Lane |
East of Nautilus Street |
September 2023 |
Winter 2027 |
6 lanes |
US 98 (Panama City Beach Parkway) |
East of Nautilus Street |
East of Richard Jackson Boulevard |
October 2023 |
Winter 2027 |
6 lanes |
Projects Scheduled to be Under Construction within Five Years | |||
Project | From | To | Improvement |
Front Beach Road |
Lullwater Drive |
Hills Road |
Multi-Modal |
Front Beach Road |
Hills Road |
Lantana Street |
Multi-Modal |
Front Beach Road |
Hutchison Boulevard |
Richard Jackson Blvd. |
Multi-Modal |
Powell Adams Road |
Front Beach Road |
South of Sting Ray Drive |
4 lanes |
DuPont Bridge |
Oakshore Drive |
Tyndall Air Force Base Boundary |
4 lanes |
Bay Parkway Phase III |
Clara Avenue |
Chip Seal Parkway |
2 lanes ROW for 4 lanes |
Minge Branch Drive Extension |
Mill Bayou Boulevard |
Titus Connector Road |
2 lanes |
Star Avenue/US 231 Realignment |
Star Avenue |
US 231 |
Realignment of Star Avenue at US 231/ Titus Road |
US 98 (Panama City Beach Parkway) |
East of Richard Jackson Boulevard |
Hathaway Bridge |
6 lanes |
If further information is needed on the status of these projects, please contact Gary Kramer gary.kramer@ecrc.org or (850) 332-7976 Ext. 219.